When Jersey Telecom decided to re-engineer and increase power and cooling capacity in their main data centre at Five Oaks, Saradan were approached to act as design consultants and client project managers.

A completely new M&E infrastructure had to be installed whilst keeping the existing customer I.T. equipment "live".

The works involved converting a large vehicle maintenance workshop into a new HV/LV switchgear room, the installation of new dual 1.5mVA mains supplies, N+N UPS system, N+1 generators and replacing the close control air conditioning.

The whole project was completed on time, to budget and with zero I.T. downtime.