Overview:

BIS Ltd, a large UK data centre provider and operator, required a complete design, fit-out and on-going maintenance solution for their new 22,500 sq/ft Greenwich data centre facility.

The building already had a part occupied computer room that needed totally refitting whilst being kept ‘live’.

New Works:

  • 18 x 80kW DX CRAC units
  • 4 x 500kVA Static UPS
  • 5 x 500kVA Diesel Generators
  • 2 x Main LV Distribution Boards
  • 2 x UPS Output Boards
  • 4 x C&E PDU’s
  • Generator AMF Panel
  • VESDA to the data halls
  • Total refit of the site
  • Dual power distribution to IT cabinets
  • Argonite gas suppression to data halls and plant room
  • TREND BMS system monitoring all M&E plant
  • CCTV internally and externally
  • Biometric and card and pin access control system
  • Forming of the external plant compound