Foreshore needed to transfer their data centre on a new, dedicated diesel generator backup system, the only space available was at the rear of two adjoining buildings at 1st floor level. Saradan were employed as design & Build contractor to design and construct for the project. The work included supply and install of the generators. a steel gantry and louvered enclosure for the generators, the new electrical switchgear required to connect the generators to the existing LV switchgear + all associated electrical works, BMS interfaces, CCTV and access control etc.
Overview
Timeframe
Saradan also had to obtain landlords approval, planning and byelaws permission for the works. The project was completed in 6 months from start to finish with no data centre downtime.